22 days early, zero budget overrun: how one company briefed its first facility right

How four disciplined steps — Prepare, Listen, Reconcile, Translate — took a team from lost to aligned.

When a Singapore-based bioprocessing company set out to build its first pilot production facility, it faced a problem familiar to any business commissioning a capital project for the first time: it knew what it wanted to achieve, but not yet what it needed to build. This is the account of how a structured process turned that uncertainty into a brief a design consultant could act on — and commissioned the facility 22 days ahead of schedule and on budget.

Case Study Bioprocessing area of a Singapore pilot production facility, delivered on budget through a structured capital project brief

Bioprocessing area of a Singapore pilot production facility, delivered on budget through a structured capital project brief.

The challenge

The Board approved the business strategy in mid-2022, setting a hard objective: operate a pilot production facility by the end of 2023, with the option to scale to commercial production two to three years later. That single sentence concealed a dense knot of difficulty.

Time was tight and the budget was rigid. The facility had to be running by end-2023 so that commissioning and the first production cycle could complete by early 2024 — yet a great deal remained undeveloped, undiscussed, and undecided.

The facility had to serve two stages of growth at once. Site location and area had to accommodate both the pilot phase and a future scale-up, avoiding the heavy fixed cost of developing a new site later. Building-services infrastructure posed the same dilemma: install larger capacity now at greater upfront cost, or save today and risk expensive additions and alterations later.

It was the company's first production facility. Coming straight out of R&D, many processes were not yet developed or verified. The design needed flexibility and room for error built in — without over-spending in the near term, and without inviting costly modifications once operations began.

Key teams did not yet exist. ERP, warehouse and logistics, and QA/QC functions had not been hired; it was considered too early to do so before the facility was built. And apart from a newly hired project manager, the staff were users and occupiers of space with no experience of a capital project.

The project manager had begun a schematic layout based on high-level use of areas, but had no reliable way to capture the operations teams' requirements into a coherent brief. Early attempts stalled: it wasn't clear what to ask, how to ask it, or how to interpret the answers. After several rounds, the team still had no confidence they had drafted something comprehensive enough to hand to a design consultant. Compounding matters, most biotech facility consultants served the pharmaceutical sector, where far higher construction specifications — and budgets — are the norm, so wherever the brief is not clear, the default position is to assume the pharmaceutical ways.

The opportunity

Handled well, the difficulties were also openings. A well-planned first phase would move the company to its next stage of growth. Smart infrastructure decisions could save money in the second phase by sharing systems across both. The standards set and verified in this phase could become the company's operational "bible" for future facilities as it expanded into new markets. And because ESG and sustainability goals ranked high in the business strategy, forward-looking environmental monitoring — GHG Scope 1, 2, and 3, water use, and waste generation — could be designed in from the start, supporting the company's longer-term impact targets rather than being retrofitted later.

The approach

The facility was delivered through a four-stage method: Prepare, Listen, Reconcile, Translate.

Prepare. A taskforce was formed, with a named person from each team — upstream bioprocessing, downstream processing, and R&D — appointed as the person-in-charge for the capital project. Crucially, every participant was first inducted into how a capital project actually works: its stages, and how their requirements and decisions would eventually translate into the built facility.

Listen. Each team was worked with in turn. Using a structured framework, each captured what it needed from the future facility in performance terms. A second set of tools then guided each team to translate those performance needs into concrete spatial and provision requirements, through closely engaged workshops conducted consistently across every team.

Reconcile. All requirements were then laid side by side. Conflicts, clashes, and gaps — the unknown and the undecided — were surfaced deliberately rather than left to emerge on site. Every stakeholder was brought into facilitated discussions to resolve them, constructively and efficiently.

Translate. Finally, the reconciled requirements were turned into a set of documents giving the design team clear, definite instructions — no guessing, no assumptions made on the teams' behalf that might prove unsuitable and surface, expensively, only during or after construction. Every team signed off the brief. The teams stayed closely involved through construction, guided on what to look for and where their input was needed.

The outcome

With intensive effort and the backing of senior management, a brief a design consultant could work from was completed in six months. The facility was commissioned 22 days ahead of the target date — handed over on 8 November 2023 against a target of 20 November 2023 — and on budget. Just as importantly, disciplined planning kept the company financially sound and healthy throughout: no overspending, no budget surprises, and no capital diverted from a business that needed every dollar working toward its next stage of growth.

Key takeaways

  1. A brief is built, not written. The quality of a capital project brief depends less on documentation skill than on a disciplined process for drawing requirements out of the people who hold them — most of whom have never briefed a building before.

  2. Alignment starts with understanding, not instruction. Inducting every team into how a capital project works — before asking them for anything — is what turns willing-but-lost contributors into effective ones.

  3. Conflicts are cheaper on paper than on site. Surfacing clashes and undecided points before design begins costs a fraction of discovering them during construction, where changes drive variations, delays, and claims.


Previous
Previous

A 15% saving the operator signed off on — by trimming requirements, not corners